Chollas
Substation Rebuild
Project
Description: Chollas Substation Rebuild - 69kV Transmission &
12kV Distribution
Contract
Amount: N/A
Owner:
San Diego Gas and Electric Company
This project
is being constructed in July of 2006. The Majority of this project
is being constructed in a two-month window.
This work
consists of Underground and Overhead Construction of Transmission
and Distribution Lines.
- Conduit and Substructure Installation inclusive of tub
type vault installations.
- Installation of 1000Kcmill underground cable.
- 12kV Make up and Connections.
- Rework of existing Overhead Facilities.
- Removal of existing Overhead Conductors.
Major
Subcontractors used for this project:
There were
no subcontractors used on the project. All work was preformed in house.