Chollas Substation Rebuild

Project Description: Chollas Substation Rebuild - 69kV Transmission & 12kV Distribution

Contract Amount: N/A

Owner: San Diego Gas and Electric Company

This project is being constructed in July of 2006. The Majority of this project is being constructed in a two-month window.

This work consists of Underground and Overhead Construction of Transmission and Distribution Lines.

- Conduit and Substructure Installation inclusive of tub type vault installations.
- Installation of 1000Kcmill underground cable.
- 12kV Make up and Connections.
- Rework of existing Overhead Facilities.
- Removal of existing Overhead Conductors.

Major Subcontractors used for this project:

There were no subcontractors used on the project. All work was preformed in house.


 

 

 

 

 